£8 million upgrade for Downpatrick treatment facility

AN £8 million programme of work will begin this summer at Downpatrick Wastewater Treatment Works (WwTW).

Announcing the work, NI Water explained it is being carried out to modernise the facility “and ensure that this critical asset can continue to meet strict environmental standards”.

The statement added: “The work, which has recently received planning permission, will be carried out in two phases, with the initial £8m-funded programme of improvements being undertaken to safeguard compliance, paving the way for a second phase of work to support economic development in the town.”

The local Wastewater Treatment Works is located off the Belfast Road.

NI Water Senior Project Manager Martin Armstrong explained that it was first constructed in 1995 and extended in 2010 to support Downpatrick’s growing population.

“To ensure that this key NI Water asset can continue to operate effectively and meet current environmental discharge consents, some of the older elements within the treatment facility need to be replaced,” Mr Armstrong added.

“The plan is to then commence a further extension of the works, within the existing site footprint, to accommodate future economic growth.

“Our contractor, BSG Civil Engineering, will mobilise on site in July to begin setting up their compound in lands to the north of the existing WwTW site and plan to undertake the improvements in two phases.

“The first phase will see the replacement of critical components of the treatment works which are nearing the end of their asset lifespan.

“This work will ensure that the treatment facility can continue to operate effectively and meet environmental discharge consents.

“This part of the upgrade, which will involve both civil construction and mechanical/electrical works, will be carried out over two years, with the treatment works remaining operational at all times.

“The early stages of the upgrade will involve significant excavation works and, therefore, vehicle movements in and out of the site and along the adjacent Belfast Road will increase for a number of weeks.

“Topsoil removal will be supervised by a qualified archaeologist.

“A second phase of improvements, to further increase the capacity of the treatment works and support future development in the Downpatrick area, will follow on subject to funding.

“This investment is good news for the Downpatrick area, with the phased works designed to fit both the immediate and longer-term needs of the town’s treatment facility.

“The improvements will deliver environmental benefits through improved protection of the Quoile River and subsequently Strangford Lough, while the second phase, subject to funding, will help to support economic and population growth in Downpatrick.”

Mourne Observer Down Recorder digital edition